[SCHEDULER-1299]  Imported Projects/Plans/Observations start in Disabled state.
Type Bug
Priority Low
Severity Trivial
Component Schedule Browser
Fixed In Version [8.08.0
Versions Affected [3.73.7
Severity Closed
Resolution Complete
Reported By Bob Denny
Resources Bob Denny
Start Date 2/11/2015

Description
To avoid sync problems, force all imported things to be in Disabled state.

Comments
2/11/2015 12:56:14 PM   Bob Denny
SVN Comment
Author rbdenny
Repository svn+ssh://rbdenny@a2_svn_dc3/home/rbdenny/svn/astro/scheduler
SVN Revision 529
Affected files /trunk/Browser/BrowserForm.cs (Modified)
/trunk/Database/Database.cs (Modified)
/trunk/Help/RelNotes.htm (Modified)
Check-in comment XML export/import from database forces status to DIsabled/Paused. Also fix icons in Schedule browser for new Project pause when importing and creating new projects. GEM:1299
2/11/2015 12:44:37 PM   Bob Denny
Found other cases where icons were the old ones for projects.